SBC pylon — Hunter Valley
SBC Pylon Engineering

17m WIDE.
18.5m TALL.
25m SPAN.

Same component repeated 17,360 times. Mega Factory built. Rail delivered. Crane installed.

← SBC Overview Pylon Design

SBC Pylon — Engineering Specification

The SBC viaduct is built on a standardised modular pylon. Per Pylon Design Rev 3, two design variants serve all phases. Both use identical structural principles — stackable precast columns, cap beam at every level, standard crane construction, dry mechanical joints, no bespoke beam launcher. Construction is in two stages: Stage 1 builds the freight viaduct (revenue from Month 20), Stage 2 adds upper structure on the running freight line.


Design Hierarchy

Phase 0.1 · First build
Design B (Phase 0/0.1/spurs)
~18.5m

Two levels built. Two expansion-ready above. The ask to government.

  • Level 1 — Freight × 3 — 150–200km/h
  • Level 2 — Maglev × 2 + service rail — 600 km/h
  • External — HVDC 6 × 2 bipolar — 72GW
  • Level 3+4 — expansion-ready stubs
Phase 0 upgrade
Design B Stage 2 upgrade
~34m

Stage 1 freight operating. Service crane on running line installs Stage 2 upper structure. No new pylons.

  • Stage 1 freight viaduct already operating
  • Level 3 — services: gas / H₂ / fibre / water
  • Level 4 — hyperloop-ready floor
  • External — HVDC arms at Level 4
Phases 1–3 national
Design A
~45–50m

Big Bertha. All services. $6M/km at Mega Factory maturity.

  • Level 1 — Freight × 3
  • Level 2 — Water conduit 10,000GL/yr
  • Level 3 — Services deck
  • Level 4 — Hyperloop
  • Level 5 — Maglev × 2 + service rail
  • External — HVDC 72GW → 108GW
Stage 1 (freight viaduct, ~$119M/km current / ~$74M/km at volume) is commissioned at Month 20 — revenue from operating freight funds Stage 2 construction on the running line. Mega Factory long-term target: ~$25M/km → ~$6M/km as production scale and Wright's Law -38% reductions compound across the full 20,000+km program.

Design B Locked Dimensions (per Pylon Design Rev 3)

17m
Outside width
18.5m
Total height
25m
Pylon span
14.5m
Inside clear
2,500mm
Leg base dia
6,100mm
Freight clear ht
ElementDimensionStatus
Outside width (leg OD to OD)17,000mmLOCKED
Inside clear width14,500mmLOCKED
Pylon span25,000mmLOCKED
Total height to top of maglev train18,400mmLOCKED
Leg base diameter2,500mmLOCKED
Leg top diameter1,600mmLOCKED
Leg height to HB1 soffit6,000mmLOCKED
HB1 + HB2 freight deck depth1,700mm + 1,700mmLOCKED
Freight deck top surface9,400mm aglLOCKED
Freight clear height6,100mmLOCKED
Connecting column diameter800mmLOCKED
HB3 + HB4 maglev deck depth1,200mm + 1,200mmLOCKED
Maglev deck top surface17,900mm aglLOCKED
HVDC arm length each side4,000mmLOCKED
Total width including HVDC25,000mmLOCKED

Three Lines on the Maglev Deck

Two maglev tracks and one central service rail. 2,300mm clear between vehicles. All three operate independently.

LinePosition from left edgePurpose
Maglev Track 13,500mm CL600 km/h passenger service
Service rail8,500mm CL — dead centreConstruction crane + maintenance. Independent operation.
Maglev Track 213,500mm CL600 km/h passenger service

Component Weights Per Bay

ComponentQtyUnit weightTotal
Footing pads245t90t
Tapered legs242t84t
HB1 freight transverse183t83t
HB2 freight deck segments10104t1,040t
Connecting columns29t18t
HB3 maglev transverse149t49t
HB4 maglev deck segments1073t734t
HVDC arms (steel)62.5t15t
Total per bay34 items~2,113t

Heaviest single lift: 104t. Required crane: 150t rail-mounted standard. 40 bays per kilometre. 17,360 bays per ~430km Phase 0 segment.


Factory Cost Per Bay

ComponentFactory cost
2 footing pads$29,600
2 tapered legs$33,800
HB1 freight transverse$94,500
HB2 freight deck × 10$669,000
2 connecting columns$5,944
HB3 maglev transverse$65,958
HB4 maglev deck × 10$566,630
HVDC arms × 6$58,932
Total per bay$1,524,364

40 bays/km × $1,524,364 = $61M/km factory cost. Total installed including site, track, systems and contingency: $235M/km current rates / $146M/km at volume (Phase 0 Stage 1 + Stage 2).